The start of sending crude oil from Gore to Jask

Technical inspection of the oil and gas industry

History The grand and national plan of the Gore to Jask pipeline It goes back to the 60s. At that time, that is, during the Iran-Iraq war, considering that alone Iran's oil export terminal He was on Khark Island and the enemy was well away Strategic and strategic Being aware of the existence of this terminal, he put this island under fire more than 2,840 times; While the number of days of war was 2 thousand 888 days. More than 2 thousand bombardment of Khark, alone Iran's oil export terminal; Always this feeling of need oil industry It has led to the fact that the occurrence of any unrest in the region will severely weaken Iran's export capacity. Especially, recently, the discussion of closing the Strait of Hormuz and the conflict between the Persian Gulf countries was also raised.(Related)

 

Inspection during construction

Head of Inspection and Technical Protection Department of Oil Engineering and Development Company (text) says: The Gore Jasak National Plan would not have been completed without internal capabilities. This project was able to set a huge chain of industries in motion with the long step taken to support domestic industries.

Gore crude oil transfer plan to JaskIt is a national and strategic plan with the support of the government and leadership National Iranian Oil Company and with the aim of creating a transfer capacity of one million barrels Crude oil in the day, Storage and export It through Jask's new terminalGuaranteeing the continuity of exports Crude oilDecentralization of Export Terminals and its diversification and sustainable development and job creation in Makran beaches is executed.(Related)

Third party inspection (Third party inspection)

Masoud Karbasian, CEO National Iranian Oil Company He stated that the national plan to transfer crude oil from Gore to Jask is the biggest project of Iran's oil industry: The production of transfer valves, the required electric pumps, the construction of 1000 kilometers of oil pipelines, along with the construction of tanks, terminals and floating spheres in the Jask region, using domestic power, shows the national determination to achieve this large and strategic plan..

He added: Gore project – Jask Due to sensitivities, several times in the stage of bed construction, pipe making, topkarani and so on… testpassed more than other projects without defects and with the best quality come to an end

 

Welding inspection and non-destructive testing

With the great step taken to support domestic industries, this project was able to move a huge chain of industries and affect a range of ore to pipes.. If I want to mention the non-technical achievements of this project in general, I must first mention the solution to the problem of providing pipes for the most strategic project of the country.. Providing this large volume of sheets and tubes with these economic conditions and under these oppressive sanctions was actually a difficult and even impossible task.. This inward look was able to find a solution to this challenge while preventing the outflow of huge amounts of currency. در ادامه باید به جلوگیری از خروج بیش از ۴۰۰ میلیون یورویی این طرح برای کشور از طریق ساخت تجهیزات در داخل کشور اشاره کنم که در حقیقت سرمایه بزرگ و دستاورد عظیمی است. مورد دیگر فعال شدن سرمایه‌ها و امکانات موجود در داخل کشور است. شرکت فولاد اکسین خوزستان توانست با دستیابی به این فناوری مشکلات پیشین خود را پشت سر گذارد. کارخانه لوله‌سازی ماهشهر After many years of closure, it started its activity again. In fact, this look inside made the wheels of a huge part of the domestic industries move by activating the factories that cooperated with this project, and by creating thousands of direct and indirect job opportunities, it played a significant role in the economic growth and prosperity of the country..(Related)

source:Shana

Industrial engineering company Fhamh ،Has level 1 qualification for consulting services in technical inspection, is proud to perform services as a contractor in this national project Quality control Installation workshop Gore-Jask Pump Pump House No. 2, Has partnerships and cooperation.

Feasibility studies ؛ Design management ؛ Economic studies

 

Studies of Construction of Corridor Comprehensive Gulf Comprehensive Lines are being implemented

Hormozgan Ports and Maritime Director General: Initially, 15 companies were connected to these lines, and according to the plan, all of them will be connected in the future Oil investment companies Located in Shahid Rajaei port They will benefit from these lines. ManagerShahid Rajaei Port Special Economic Zone had an expression: With the construction of the Corridor of the Gulf Port Comprehensive Lines in addition to increasing the volume of operations Discharge and loading of petroleum products, The productivity of the docks has also increased, and consequently we will see a decrease in the durability of vessels in the harbor.…(Read more)