The laying of the first marine line of the Jask oil terminal was finished

project manager Jask oil terminal He said: Construction operation of the first 36-inch marine pipeline to transfer crude oil Jask export terminal completed.

According to Shana report, quoting from Pars Oil and Gas Company, Vahid Maliki stated that the pipe-laying operation of this 6-kilometer pipeline was carried out in two stages by the C-Master pipe-laying float.: The first stage of the construction of this pipeline was carried out by stretching the sea pipeline from the coast to a length of 2.5 km from a depth of 10 meters from the seabed to the coast..

He stated that in the second stage of the construction of this marine pipeline, the remaining 3.5 km piping operation from a depth of 10 meters to the offshore position of the first export floating sphere. Jask oil terminal to a depth of 55 meters from Sunday (5th of Bahman) It started, he stated: This operation is with the round-the-clock efforts of the contractor's team in the offshore sector Supervision Continuous project employer, in the early hours of today (Wednesday, the 8th of February) It ended.

According to the supervisor Jask oil terminal planC Master pipe-laying float to complete the sea route of the first floating sphere exportToday, in the position of the second line of the 36-inch marine pipeline Oil terminal will be deployed.

Total ownership of marine pipelines Jask oil terminal 45 km including 6 36-inch pipeline lines and predicted until the end of February. Tubing The early launch route will be completed in both land and sea sectors.

He stated that with the installation of two 36-inch marine pipelines, each 6 kilometers long, by the end of next week, it will be possible to load and transfer the first marine facilities, including submarine multi-lanes and floating spheres. export From Khorramshahr Industrial Yard, it will be installed in the waters of the Oman Sea in early March of this year, he said.: In this way, with the installation and operation of marine facilities until the end of March, it is possible Export of crude oil from the sea of ​​Oman for The first time in the country is provided.

supervisor Jask oil terminal plan He announced and stated that the overall progress of the project in the early phase is more than 75%: This project in the department Engineering It has reached 85% progress and also 90% of the required goods Jask oil terminal plan provided.

Jask oil terminal development plan As the last link in the chain of national and strategic plans Transfer of crude oil from Gore to Jask, including three sets of 48-inch land pipelines and measuring systems, 6 36-inch submarine pipelines, three sets of marine multi-lanes and three sets of floating spheres along with peripheral equipment, the first phase of which is scheduled to be put into operation by the end of this year.

source:Shana

Oil and gas industry

The project of transferring crude oil from Gore to Jask, the objectives of the project:Transferring one million barrels of light and heavy crude oil from Gore to Jask and exporting from the new Jask terminal…(Read more)

Industrial engineering company Fhamh, Specialized service provider TECHNICAL INSPECTION , third party inspection,Feasibility studies and preparation of justification (Technical-Economic)، Management Advice, Investment Advice, supervision, control and management of projects Oil, gas, petrochemical and refinery industries Country.

The end of piping the first marine line of Jask oil terminal

According to IRNA's report on Wednesday, from Pars Oil and Gas Company, "Vahid Maliki" by reminding that the first stage of the construction of this pipeline is by tension method. Sea pipeline from the coast (Shore Pulling) It was carried out for 2.5 kilometers from the depth of 10 meters from the seabed to the shore, he said: In the second stage of the construction of this marine pipeline..(Read more)

Product inspection of oil and gas industries ؛ GOODS INSPECTION ؛